Site diary in pictures and words
Completed heating distribution in the apartments
22.04.2017.
Setting up the EPDM membrane on the terrace
13.04.2017.
Painting work
03.04.2017.
Baking ceramics
03.04.2017.
Start lubrication waterproofing
01.04.2017.
Completion of mortar
27.03.2017.
Completion of the demit facade
25.03.2017.
Start cement mortar
15.03.2017.
Finished setting up the facade of PVC
26.11.2016.
Production of heat insulation
26.11.2016.
Machine plastering interior walls
24.10.2016.
Setting window
22.09.2016.
A wooden roof structure
17.09.2016.
Concreting roof beams
29.08.2016.
Concrete slab roof pulled floor
10.08.2016.
Concreting of columns and walls pulled floor
04.07.2016.
Concrete slab floor of an attic floor
18.06.2016.
Raising walls 1. floor
30.05.2016.
Concrete slab floors 5
28.05.2016.
Concrete slab fourth floor
09.05.2016.
Concrete slab 3rd floor
12.04.2016.
Concrete slab of the second floor
19.03.2016.
Shuttering plates of the second floor
05.03.2016.
Concreting of the first floor slab
08.02.2016.
Installing reinforcement first floor slab
04.02.2016.
Setting of first floor slab formwork
26.01.2016.
Raising walls of the ground floor
29.12.2015.
Concreting walls of the ground floor
26.12.2015.
Concreting of the zero panel
16.12.2015.
Concreting of basement walls
04.12.2015.
Installing reinforcement for the base plate
13.11.2015.
Concreting thin plate
11.11.2015.
Setting a buffer layer of gravel
11.11.2015.
Completion of the excavation
10.11.2015.
Finishing concrete of retaining wall
06.11.2015.
Excavation of earth for retaining wall
02.11.2015.
Completion of demolition
30.10.2015.